| Code | PIC-205-01 |
|---|---|
| General commentary | |
| The pictures in this visual example were taken during a training event held in Tirana, Albania. The site was a large depot where imported oil was stored before distribution. There was no oil refinery at this location. This was a demonstration of sampling from a large static tank. | |
| Equipment needed | |
| Safety precautions and risk assessment | |
Please refer to your national legislation and guidelines on health and safety.
For general precautions see EN ISO 3170.
Personal protective equipment:
| |
| Sampling plan | |
| One aggregate sample from three incremental samples at different heights: approximately 15 % from the bottom, half-way up and approx. 15 % from the top surface of the product in the tank. Check the homogeneity of the lot — if the homogeneity is in doubt, take more incremental samples. | |
| Links | SAM-205 Petroleum liquids |
| Remark | Tariff classification: 2710 Petroleum oils and oils obtained from bituminous minerals |
| Tags | Heating Oil, Static Tank, Mineral Oil |
| This material should only be used in connection to a proper sampling plan | |
Order of displayed pictures Comment | |
PIC-205-02-A01 When arriving on an unfamiliar site make sure you understand the general situation including the full range of risks associated with any product on site regardless of the particular product you are sampling. In this case the storage facility held petrol, aviation fuel, diesel and heating oil. Whilst the heating oil has a relatively high flash-point – other products carry a much greater risk of fire so adequate precautions should be taken at all times. | |
PIC-205-02-A02
This is a very comprehensive list and not all items will be required for each task. | |
PIC-205-02-A03 Assess the access to the sampling site. In this case there are numerous pipes and cables. Great care must be used to avoid trips and falls. | |
PIC-205-02-A04
| |
PIC-205-02-A05 Preparing the sampling tools
The sampling point showing:
The sampling will be carried out by a company representative and supervised by the officer. | |
PIC-205-02-A06 The dipping vessel is lowered into the tank to the correct depth and the secondary cord pulled sharply to remove the bung allowing the sample to flow into the vessel.
The very top and bottom are avoided as there may be contamination from water at the bottom or surface debris at the top which are not representative of the product. | |
PIC-205-02-A06
The very top and bottom are avoided as there may be contamination from water at the bottom or surface debris at the top which are not representative of the product. | |
PIC-205-02-A07 The incremental samples are placed in the bucket and thoroughly mixed to create the aggregate sample. Wear gloves during this action. | |
PIC-205-02-A08 Descending from the tank. | |
PIC-205-02-A09 The sampling is complete. A box is used to transport them. | |
Samples must be stored appropriately. The sampling form must be completed fully and the sample sent to the laboratory. | |